Key Takeaways

  • Earned Value Management (EVM) integrates scope, schedule, and cost data to measure project performance objectively
  • CPI (Cost Performance Index) = EV/AC measures cost efficiency; CPI > 1.0 means under budget, CPI < 1.0 means over budget
  • SPI (Schedule Performance Index) = EV/PV measures schedule efficiency; SPI > 1.0 means ahead of schedule
  • EAC (Estimate at Completion) = BAC/CPI forecasts total project cost if current cost trends continue
  • TCPI (To-Complete Performance Index) calculates the efficiency needed for remaining work to meet budget or revised estimate
Last updated: January 2026

Cost Management

Cost management involves planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget. In predictive projects, the cost baseline is established during planning and managed through earned value techniques.

Cost Management Processes

ProcessPurposeKey Output
Plan Cost ManagementDefine policies and proceduresCost Management Plan
Estimate CostsDevelop cost approximationsActivity Cost Estimates
Determine BudgetEstablish authorized cost baselineCost Baseline
Control CostsMonitor status and manage changesWork Performance Information

Cost Estimating Techniques

Estimation Methods Comparison

TechniqueDescriptionAccuracyWhen to Use
Analogous (Top-Down)Use similar past project data-25% to +75%Early estimates, limited data
ParametricUse statistical relationships-10% to +25%When parameters are known
Bottom-UpEstimate each work package, aggregate-5% to +10%Detailed planning phase
Three-PointUse optimistic, most likely, pessimisticVariesWhen uncertainty exists

Three-Point Estimating Formulas

DistributionFormulaUse Case
TriangularE = (O + M + P) / 3Equal weight to all estimates
Beta (PERT)E = (O + 4M + P) / 6More weight to most likely
Standard DeviationSD = (P - O) / 6Measure of uncertainty
VarianceV = [(P - O) / 6]^2For summing uncertainties

Example: Three-Point Estimate

Estimate TypeDays
Optimistic (O)4
Most Likely (M)6
Pessimistic (P)14

Beta (PERT) Estimate = (4 + 4(6) + 14) / 6 = (4 + 24 + 14) / 6 = 42/6 = 7 days

Standard Deviation = (14 - 4) / 6 = 10/6 = 1.67 days


Cost Baseline and Budget

Components of Project Budget

ComponentDescription
Activity Cost EstimatesCost for each work package
Contingency ReservesKnown-unknown risks (part of baseline)
Cost BaselineAuthorized time-phased budget
Management ReservesUnknown-unknown risks (not in baseline)
Project BudgetCost Baseline + Management Reserves

Earned Value Management (EVM)

EVM is a methodology that integrates scope, schedule, and cost data to measure project performance objectively. It answers three fundamental questions:

  1. Where are we compared to where we planned to be?
  2. How efficiently are we using our resources?
  3. What do we expect the project to cost at completion?

Core EVM Values

MetricFormulaDescription
PV (Planned Value)From schedule baselineValue of work PLANNED to be done
EV (Earned Value)% Complete x BACValue of work ACTUALLY done
AC (Actual Cost)From accountingCost ACTUALLY incurred
BAC (Budget at Completion)Original budgetTotal budgeted cost for the project

Understanding EV

EV answers: "What is the budgeted value of the work we've actually completed?"

Example: If a $100,000 project is 40% complete, EV = $40,000


EVM Variance Analysis

Variance Formulas

VarianceFormulaInterpretation
CV (Cost Variance)EV - ACPositive = Under budget
SV (Schedule Variance)EV - PVPositive = Ahead of schedule

Variance Example

MetricValue
BAC$100,000
PV (Planned)$50,000
EV (Earned)$45,000
AC (Actual)$60,000

CV = EV - AC = $45,000 - $60,000 = -$15,000 (Over budget by $15,000)

SV = EV - PV = $45,000 - $50,000 = -$5,000 (Behind schedule by $5,000 of work)


EVM Performance Indices

Index Formulas

IndexFormulaInterpretation
CPI (Cost Performance Index)EV / AC> 1.0 = Under budget
SPI (Schedule Performance Index)EV / PV> 1.0 = Ahead of schedule

Memory Aid for Interpretation

Index ValueCost (CPI)Schedule (SPI)
> 1.0Under budgetAhead of schedule
= 1.0On budgetOn schedule
< 1.0Over budgetBehind schedule

Index Example (Using Previous Values)

CPI = EV / AC = $45,000 / $60,000 = 0.75 (For every $1 spent, only $0.75 of value earned)

SPI = EV / PV = $45,000 / $50,000 = 0.90 (Only 90% of planned work completed)


EVM Forecasting

Estimate at Completion (EAC) Formulas

ScenarioFormulaWhen to Use
Atypical VarianceEAC = AC + (BAC - EV)Past variances won't continue
Typical VarianceEAC = BAC / CPICurrent cost trends will continue
Schedule & Cost ImpactEAC = AC + [(BAC - EV) / (CPI x SPI)]Both affect remaining work
Bottom-Up Re-estimateEAC = AC + ETCWhen original estimate is flawed

Other Forecasting Formulas

MetricFormulaDescription
ETC (Estimate to Complete)EAC - ACCost needed to finish remaining work
VAC (Variance at Completion)BAC - EACExpected over/under run at completion

Forecasting Example

Using CPI = 0.75, BAC = $100,000, EV = $45,000, AC = $60,000:

EAC = BAC / CPI = $100,000 / 0.75 = $133,333

ETC = EAC - AC = $133,333 - $60,000 = $73,333

VAC = BAC - EAC = $100,000 - $133,333 = -$33,333 (Expected $33,333 over budget)


To-Complete Performance Index (TCPI)

TCPI calculates the cost performance required for remaining work to meet a target:

TCPI Formulas

TargetFormulaUse
Meet BACTCPI = (BAC - EV) / (BAC - AC)To finish within original budget
Meet EACTCPI = (BAC - EV) / (EAC - AC)To finish at revised estimate

TCPI Interpretation

TCPI ValueMeaning
> 1.0Must be MORE efficient to meet target (harder)
= 1.0Continue at same efficiency
< 1.0Can be LESS efficient and still meet target (easier)

TCPI Example

BAC = $100,000, EV = $45,000, AC = $60,000

TCPI to meet BAC = (BAC - EV) / (BAC - AC) = ($100,000 - $45,000) / ($100,000 - $60,000) = $55,000 / $40,000 = 1.375

Interpretation: Must achieve CPI of 1.375 on remaining work to meet original budget — very challenging!


Complete EVM Formula Reference

AcronymNameFormulaInterpretation
PVPlanned ValueSchedule baselineWork planned
EVEarned Value% Complete x BACWork done
ACActual CostAccounting dataCost incurred
BACBudget at CompletionOriginal budgetTotal budget
CVCost VarianceEV - AC+/- = Under/Over
SVSchedule VarianceEV - PV+/- = Ahead/Behind
CPICost Performance IndexEV / AC> 1 = Under budget
SPISchedule Performance IndexEV / PV> 1 = Ahead
EACEstimate at CompletionBAC / CPI (typical)Forecast total cost
ETCEstimate to CompleteEAC - ACRemaining cost
VACVariance at CompletionBAC - EACOver/Under at end
TCPITo-Complete Performance Index(BAC-EV)/(BAC-AC)Required efficiency

Key Takeaways

  • EVM integrates scope, schedule, and cost for objective performance measurement
  • EV (Earned Value) = % Complete x BAC represents the value of work accomplished
  • CPI = EV/AC measures cost efficiency (> 1.0 = under budget)
  • SPI = EV/PV measures schedule efficiency (> 1.0 = ahead of schedule)
  • EAC = BAC/CPI forecasts final cost if current trends continue
  • TCPI shows the efficiency required on remaining work to meet a target
EVM Example: Project at Reporting Date ($)
Test Your Knowledge

A project has BAC = $200,000, EV = $80,000, and AC = $100,000. What is the Cost Performance Index (CPI)?

A
B
C
D
Test Your Knowledge

Using the same project data (BAC = $200,000, EV = $80,000, AC = $100,000), what is the Estimate at Completion (EAC) if current cost trends continue?

A
B
C
D
Test Your Knowledge

A project shows SV = -$10,000 and CV = +$5,000. What does this indicate about project status?

A
B
C
D